Judge threatens to force PG&E to hire more tree trimmers

Judge threatens to force PG&E to hire more tree trimmers
I’M TONI VALLIERE. KCRA 3’S TAMARA BERG JOINS US WITH A LOOK AT YOUR FORECAST. IT IS CALM NOW, BUT A STORM IS ON ITS WAY. TAMARA: I AM EXPECTING AT AROUND SUNRISE. ABOUT 7:00 A.M., WE WILL START TO SEE HEAVY RAIN IMPACTING THE VALLEY SPOTS, AND ALONG WITH THE SIERRA SNOW STARTING AT THAT POINT. IT IS 4:00 A.M., THE ROADS ARE DRY UNDER OVERCAST SKIES. TEMPERATURES STARTING IN THE 40’S, LOW TO MID 40’S. ONCE WE GET PAST SUNRISE, WINDS ARE MOVING UP, ABOUT 15-20 MILES PER HOUR SUSTAINED AS THE RAIN KICKS THROUGH. WE WILL SEE HEAVY RAIN TIMING OUT LIKELY BETWEEN 9:00 A.M. AND NOON. ONCE WE GET PAST NOON, A CHANCE OF THUNDERSTORMS DEVELOPING. ONCE THE SNOW STARTS IN THE SIERRA, IT WILL BE STICKING AROUND, SNOWFALL RATES ABOUT TWO INCHES PER HOUR AS WE GET INTO THE BACK HALF OF TODAY. I WOULD NOT ADVISE SIERRA TRAVEL LATER THAN 6:00
Advertisement
Judge threatens to force PG&E to hire more tree trimmers
A federal judge on Thursday threatened to force Pacific Gas & Electric to hire more tree trimmers to reduce the chances of its electrical grid igniting fires in Northern California and adhere to a requirement imposed after the utility's natural gas lines blew up a neighborhood a decade ago.U.S. District Judge William Alsup notified PG&E that he expects more precautions to be taken, which comes a day after the San Francisco company acknowledged in a court filing that as many as 22,000 trees in its sprawling service territory may still be creating fire hazards. Those dangers are one reason the nation's largest utility has resorted to deliberately turning off the power in dry, windy and hot conditions - a strategy that at one point left an estimated 2 million people without power in October.PG&E has said the deliberate blackouts could be a recurring event for the next decade while it spends billions of dollars to upgrade its outdated electrical grid. Alsup said he thinks that reliance on blackouts stems in part from PG&E's tree-trimming shortcomings. The company said it will respond to Alsup by his Feb. 12 deadline. In its disclosure Wednesday to the judge, PG&E asserted it's unrealistic to expect it to be able to ensure all trees are maintained in a way that ensures all the branches, leaves and other vegetation remain a safe distance from its transmission lines.“Perfect compliance would require nothing less than round-the-clock surveillance" of the tens of millions of trees that it estimates could come into contact with its lines in an expanse covering about 70,000 square miles, PG&E wrote in the filing. But Alsup was apparently unswayed, noting that PG&E had blamed some of its problems on not being able to find enough contractors to do the work. Now, he is mulling whether he should issue an order that would require PG&E to hire and train more people to do the tree-trimming work. The requirement expanding PG&E's payroll could come at the same time the utility is mired in bankruptcy. It's trying to dig out of a financial hole created after its transmission lines were blamed for a series of catastrophic wildfires in 2017 and 2018. Those blazes left the company with more than $50 billion in claimed losses, a liability that PG&E is trying to erase in bankruptcy court by June 30.Alsup isn't involved in the bankruptcy case, but he has oversight over PG&E as part of a five-year probation slapped on the company in 2017 following its criminal conviction for a natural gas explosion in 2010 that killed eight people and destroyed 38 homes in San Bruno, California. The judge scheduled a Feb. 19 hearing to determine whether he should make hiring more tree trimmers a new condition of that probation.

A federal judge on Thursday threatened to force Pacific Gas & Electric to hire more tree trimmers to reduce the chances of its electrical grid igniting fires in Northern California and adhere to a requirement imposed after the utility's natural gas lines blew up a neighborhood a decade ago.

U.S. District Judge William Alsup notified PG&E that he expects more precautions to be taken, which comes a day after the San Francisco company acknowledged in a court filing that as many as 22,000 trees in its sprawling service territory may still be creating fire hazards.

Advertisement

Those dangers are one reason the nation's largest utility has resorted to deliberately turning off the power in dry, windy and hot conditions - a strategy that at one point left an estimated 2 million people without power in October.

PG&E has said the deliberate blackouts could be a recurring event for the next decade while it spends billions of dollars to upgrade its outdated electrical grid. Alsup said he thinks that reliance on blackouts stems in part from PG&E's tree-trimming shortcomings.

The company said it will respond to Alsup by his Feb. 12 deadline. In its disclosure Wednesday to the judge, PG&E asserted it's unrealistic to expect it to be able to ensure all trees are maintained in a way that ensures all the branches, leaves and other vegetation remain a safe distance from its transmission lines.

“Perfect compliance would require nothing less than round-the-clock surveillance" of the tens of millions of trees that it estimates could come into contact with its lines in an expanse covering about 70,000 square miles, PG&E wrote in the filing.

But Alsup was apparently unswayed, noting that PG&E had blamed some of its problems on not being able to find enough contractors to do the work. Now, he is mulling whether he should issue an order that would require PG&E to hire and train more people to do the tree-trimming work.

The requirement expanding PG&E's payroll could come at the same time the utility is mired in bankruptcy. It's trying to dig out of a financial hole created after its transmission lines were blamed for a series of catastrophic wildfires in 2017 and 2018. Those blazes left the company with more than $50 billion in claimed losses, a liability that PG&E is trying to erase in bankruptcy court by June 30.

Alsup isn't involved in the bankruptcy case, but he has oversight over PG&E as part of a five-year probation slapped on the company in 2017 following its criminal conviction for a natural gas explosion in 2010 that killed eight people and destroyed 38 homes in San Bruno, California.

The judge scheduled a Feb. 19 hearing to determine whether he should make hiring more tree trimmers a new condition of that probation.