Land permits delay work for Mumbai-Ahmedabad bullet train in Maharashtra | Mumbai news - Hindustan Times
close_game
close_game

Land permits delay work for Mumbai-Ahmedabad bullet train in Maharashtra

Hindustan Times | By, Mumbai
Sep 09, 2018 12:13 AM IST

Meanwhile, NHSRCL has made considerable progress in Gujarat, especially Ahmedabad and Vadodara.

About a year after Prime Minister Narendra Modi and his Japanese counterpart Shinzo Abe laid the foundation stone for India’s first high-speed rail in September 2017, hardly any work has begun in Mumbai and other parts of the state. Meanwhile, preparatory work is being undertaken in full swing in Gujarat.

Of the 508.17-km long corridor, 155.76 km will be in Maharashtra(HT file photo)
Of the 508.17-km long corridor, 155.76 km will be in Maharashtra(HT file photo)

Of the 508.17-km long corridor, 155.76 km will be in Maharashtra, 348.04 km in Gujarat and 4.3 km in Dadra and Nagar Haveli. The National High Speed Rail Corporation Limited (NHSRCL) is in the process of acquiring land with the help of the state governments. NHSRCL has to acquire 1,434 hectares of land from 298 villages in Gujarat and 350 hectares from 104 villages in Maharashtra.

Hindustan Times - your fastest source for breaking news! Read now.

A joint measurement survey to finalise the alignment and land required has been completed in most villages in Thane district, but there is strong opposition in Palghar, said NHSRCL officers. About 109.06 km of the corridor will pass through Palghar.

NHRSCL has gotten possession of the required land in Bandra Kurla Complex, which will serve as the starting point in the city for the bullet train. Godrej-owned land in Vikhroli has also been sought for the tunnel-boring machines, but the issue is pending in court. “Within two to three months, we will invite tenders for the shaft from where tunnel-boring machines will be lowered for digging tunnels at Vikhroli,” said Dhananjay Kumar, a spokesperson of NHSRCL.Meanwhile, NHSRCL has made considerable progress in Gujarat, especially Ahmedabad and Vadodara. The tendering process to develop a multi-storeyed hub on a 13-acre plot in Sabarmati is underway.

NHRSCL has also begun work on the transplantation of full-grown trees from a plot that will serve as the maintenance facility for the bullet train. Construction for a new container depot for Container Corporation Of India Limited (CONCOR) has begun at Khodiyar and construction of a training institute for train pilots has begun in Vadodara. While the project is set to be launched in 2023, the first stretch of the bullet train is expected to be inaugurated between Surat and Billimora by 2022.

SHARE THIS ARTICLE ON
Share this article
  • ABOUT THE AUTHOR
    author-default-90x90

    Kailash works with the political team and has been covering transport beat for over a decade. He is interested in travel and music.

SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Friday, March 29, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On