Andamans to get undersea cable

The nearly 2,200-km-long optical fibre system will run between Chennai and the islands

December 24, 2018 01:09 am | Updated 07:49 am IST - CHENNAI

A proposal to provide high speed internet to the Andaman and Nicobar Islands in order to augment their communication infrastructure especially during natural disasters through an under-sea optical fibre cable system from Chennai has been cleared by an expert committee of the Ministry of Environment, Forest and Climate Change (MoEF).

The ‘Chennai Andaman Nicobar Island’ (CANI) cable system will have a speed of 100 Gigabit per second and “will be of immense strategic significance to India in addition to assisting the Andaman and Nicobar Islands communications security, especially during natural disasters or failures of other systems”, the Department of Telecoms submitted before the Expert Appraisal Committee (EAC) of the MoEF.

The proposed project is set to provide a fillip to defence communication infrastructure in the islands. At present, telecom connectivity between the mainland and Andaman and Nicobar is through satellites with limited bandwidth capacity.

Eight islands

The project is expected to be implemented at a cost of ₹71.28 crore. The sub-marine cable system will connect the Indian mainland from Chennai with the eight islands of the Union Territory. These are Port Blair, Little Andaman (Hut Ba), Car Nicobar, Kamorta, Great Nicobar (Campbell Bay), Havelock, Long and Rangat.

Under the proposal, the sub-marine cable system will be laid on the sea bed and the total route length will be 2,199.66 km.

The cable will land at the beaches and terminate at the proposed beach manhold (BMH) locations and then taken to the cable landing station (CLS) for distribution.

NIOT’s involvement

“All 8 BMHs and 3 CLS are falling within the Island Coastal Regulation Zone (ICRZ) area as per the survey conducted by Institute of Remote Sensing (IRS), Anna University, Chennai,” the minutes of the EAC meeting read.

Noting that some form of damage to the corals in the region was inevitable along the cable route, the EAC directed the Department to limit the damage by creating adequate safeguards, and carry out additional marine Environmental Impact Assessment study through the National Institute of Ocean Technology (NIOT), Chennai, as part of the Detailed Project Report.

“The Committee observed that, this study is required as abundant precaution in addition to the study report made available. The study should also highlight conservation and restoration measures for corals and associated flora and fauna,” it added.

The committee also directed that NIOT be associated as a third party observer for the project until its completion and provide appropriate advice during its implementation.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.