Vienna Paving Schedule September and October
Published: Sep. 19, 2019 at 11:12 AM EDT
The following streets are part of the 2019 Vienna street paving schedule...
September 18 & 19: 3rd Ave. Rivercrest Cir. to 46th Street.
September 19: 40th Street River Rd. to 3rd Ave.
September 20-25: 41st Street River Rd. to Grand Central Ave.
September 27: 15th Ave. 3200 block
September 30: 16th Ave. 30th Street to 32nd Street
October 1: Crestview Dr.
October 2 & 3: 19th Ave. 28th Street to 29th Street including 29th Street
October 4: 18th Ave. 28th Street to dead end
October 7-10: Woodland Dr. and Valley View Dr.
October 14: Ballfield and Walking Trail